Sin Lian Heng Construction v. Singapore Telecommunications: Breach of Contract & Cable Recovery Dispute
In a consolidated suit before the High Court of Singapore, Sin Lian Heng Construction Pte Ltd (SLH) sued Singapore Telecommunications Ltd (Singtel) for $2,130,926.08 in unpaid work under a contract for cable laying and recovery. Singtel counterclaimed for breach of contract, conversion, and detention of cables. The court allowed SLH's appeal in part, reducing the damages owed by SLH to Singtel to $1,719,211.90, after accounting for a performance bond.
1. Case Overview
1.1 Court
High Court1.2 Outcome
Appeal Allowed in Part
1.3 Case Type
Civil
1.4 Judgment Type
Grounds of Decision
1.5 Jurisdiction
Singapore
1.6 Description
SLH sued Singtel for unpaid work; Singtel counterclaimed for breach of contract and cable conversion. The court partially allowed SLH's appeal, reducing damages owed to Singtel.
1.7 Decision Date
2. Parties and Outcomes
Party Name | Role | Type | Outcome | Outcome Type | Counsels |
---|---|---|---|---|---|
Singapore Telecommunications Ltd | Defendant, Appellant | Corporation | Judgment for Defendant | Won | |
Sin Lian Heng Construction Pte Ltd | Plaintiff, Respondent | Corporation | Appeal Allowed in Part | Partial |
3. Judges
Judge Name | Title | Delivered Judgment |
---|---|---|
Lee Seiu Kin | Judge | Yes |
4. Counsels
4. Facts
- SLH contracted with Singtel for cable laying and recovery works.
- Singtel claimed SLH failed to return all recovered cables.
- SLH disputed Singtel's measurements of cable lengths.
- Singtel relied on as-built drawings to prove cable quantities.
- SLH alleged cables were missing before they arrived at the site.
- SLH claimed Singtel supervisors were present during recovery works.
- Singtel obtained summary judgment for the return of cables or their value.
5. Formal Citations
- Sin Lian Heng Construction Pte Ltd v Singapore Telecommunications Ltd, Suit No 525 of 2006 (Registrar's Appeal No 314 of 2008) and Suit No 532 of 2006, [2010] SGHC 215
6. Timeline
Date | Event |
---|---|
SLH commenced Suit 525 against Singtel | |
Singtel commenced Suit 532 against SLH | |
Assessment carried out by the assistant registrar | |
AR rendered decision assessing damages to Singtel at $5,211,711.92 | |
SLH filed registrar’s appeal no 314 of 2008 | |
Court allowed SLH’s appeal in part and reduced the quantum of damages to $1,891,891.90 | |
Court gave grounds of decision |
7. Legal Issues
- Breach of Contract
- Outcome: SLH found liable for breach of contract for failing to return cables.
- Category: Substantive
- Sub-Issues:
- Failure to return cables
- Conversion of cables
- Admissibility of Evidence
- Outcome: Court rejected Singtel's evidence regarding the quantity of cables recovered due to lack of admissible evidence.
- Category: Procedural
- Sub-Issues:
- Failure to call witnesses
- Proof of as-built drawings
8. Remedies Sought
- Monetary Damages
- Delivery of Cables
9. Cause of Actions
- Breach of Contract
- Conversion
- Detention of Cables
10. Practice Areas
- Commercial Litigation
- Construction Disputes
11. Industries
- Construction
- Telecommunications
12. Cited Cases
Case Name | Court | Affirmed | Citation | Jurisdiction | Significance |
---|---|---|---|---|---|
Evidence Act | N/A | Yes | s 116 of Evidence Act (Cap 97, 1997 Rev Ed) | Singapore | Cited for the principle that a party's failure to produce evidence within its power to produce suggests the evidence is unfavorable to that party. |
13. Applicable Rules
Rule Name |
---|
No applicable rules |
14. Applicable Statutes
Statute Name | Jurisdiction |
---|---|
Evidence Act (Cap 97, 1997 Rev Ed) | Singapore |
15. Key Terms and Keywords
15.1 Key Terms
- Cable Recovery
- Service Order
- Daily Pulling Summary Report
- As-Built Drawings
- Performance Bond
- Cable Laying
- Cable Shortfall
15.2 Keywords
- breach of contract
- cable recovery
- construction
- singtel
- sin lian heng
- damages
- singapore
17. Areas of Law
Area Name | Relevance Score |
---|---|
Breach of Contract | 75 |
Contract Law | 70 |
Damages | 65 |
Evidence Law | 60 |
Civil Procedure | 50 |
Torts | 30 |
Performance Bond | 20 |
16. Subjects
- Contract Dispute
- Construction Dispute
- Cable Recovery