Bintai Kindenko v Samsung C&T: Interlocutory Injunction on Banker's Guarantee & Exclusion Clauses
In Bintai Kindenko Private Limited v Samsung C&T Corporation and DBS Bank Ltd, the Singapore High Court addressed an application by Samsung C&T Corporation to lift an interim injunction obtained by Bintai Kindenko Private Limited, restraining DBS Bank Ltd from paying out on a banker’s guarantee. The guarantee was issued in favor of Samsung C&T Corporation pursuant to a subcontract with Bintai Kindenko Private Limited. Samsung C&T Corporation called on the guarantee due to alleged breaches of the subcontract. The High Court lifted the injunction, finding that an exclusion clause in the subcontract precluded Bintai Kindenko Private Limited from raising unconscionability as a ground for resisting the call on the guarantee, and that fraud was not established. Bintai Kindenko Private Limited appealed the decision, and leave to appeal was granted by the Court of Appeal.
1. Case Overview
1.1 Court
High Court of Singapore1.2 Outcome
Injunction discharged; appeal granted by the Court of Appeal.
1.3 Case Type
Civil
1.4 Judgment Type
Grounds of Decision
1.5 Jurisdiction
Singapore
1.6 Description
Singapore High Court case regarding an interim injunction to restrain payment on a banker's guarantee due to alleged breaches of contract.
1.7 Decision Date
2. Parties and Outcomes
Party Name | Role | Type | Outcome | Outcome Type | Counsels |
---|---|---|---|---|---|
DBS Bank Ltd | Defendant | Corporation | Neutral | Neutral | |
Samsung C&T Corporation | Defendant | Corporation | Injunction lifted | Won | |
Bintai Kindenko Private Limited | Plaintiff | Corporation | Injunction discharged | Lost |
3. Judges
Judge Name | Title | Delivered Judgment |
---|---|---|
Aedit Abdullah | Judge | Yes |
4. Counsels
4. Facts
- Plaintiff and 1st Defendant entered into a subcontract in December 2012 for mechanical, electrical, and plumbing works.
- A banker’s guarantee of about $4.3m was issued by the 2nd defendant in favour of the 1st defendant.
- The 1st defendant imposed liquidated damages and sought to call on the guarantee due to alleged contractual breaches.
- The plaintiff sought and obtained an interim injunction against the demand and payment on an ex parte basis.
- The 1st defendant applied to lift the injunction.
- The subcontract incorporates a clause which expressly stipulates that except in the case of fraud, the plaintiff shall not for any reason whatsoever be entitled to enjoin or restrain the 1st defendant on making any call or demand on the guarantee.
- The 1st defendant eventually filed an application to set aside the adjudication determination.
5. Formal Citations
- Bintai Kindenko Pte Ltd v Samsung C&T Corp and another, Suit No 800 of 2017, [2018] SGHC 191
6. Timeline
Date | Event |
---|---|
Subcontract entered into by the 1st defendant and the plaintiff for the supply and installation of mechanical, electrical and plumbing works. | |
Completion dates for the various phases of the works to be done spanned March 2013 to April 2014. | |
Completion dates for the various phases of the works to be done spanned March 2013 to April 2014. | |
Plaintiff achieved actual completion of the last phase. | |
Letters exchanged from the period of May 2015 to January 2016, where the 1st defendant sought to pin responsibility for the delay on the plaintiff and notified the plaintiff of potential liquidated damages to be paid. | |
Letters exchanged from the period of May 2015 to January 2016, where the 1st defendant sought to pin responsibility for the delay on the plaintiff and notified the plaintiff of potential liquidated damages to be paid. | |
Payment claims filed by the plaintiff, and responses from the 1st defendant detailing reasons for withholding payments and indicating liquidated damages payable by the plaintiff were then exchanged between February 2017 and July 2017. | |
Payment claims filed by the plaintiff, and responses from the 1st defendant detailing reasons for withholding payments and indicating liquidated damages payable by the plaintiff were then exchanged between February 2017 and July 2017. | |
Plaintiff lodged an adjudication application against the 1st defendant in relation to the first half of the retention monies. | |
An adjudicator was appointed. | |
The adjudication determination was granted in favour of the plaintiff; no determination was made on the variation order claims and back charges. | |
The 1st defendant replied with a payment response explaining why payments were withheld. | |
The 1st defendant made a demand on the banker’s guarantee. | |
Plaintiff obtained an interim injunction against the demand and payment on an ex parte basis. | |
Hearing date. | |
Hearing date. | |
The matter was heard on 14 November 2017 by Foo Chee Hock JC. | |
Hearing date. | |
Date of judgment. |
7. Legal Issues
- Interlocutory Injunction
- Outcome: The court discharged the interim injunction.
- Category: Procedural
- Sub-Issues:
- Ex parte application
- Full and frank disclosure
- Unconscionability
- Outcome: The court found that unconscionability was precluded by the subcontract between the parties due to the exclusion clause.
- Category: Substantive
- Related Cases:
- [2015] 3 SLR 1041
- Fraud
- Outcome: The court found that fraud was not established on the facts.
- Category: Substantive
- Sub-Issues:
- Dishonest conduct
- Reckless indifference to the truth
- Incorporation of Exclusion Clause
- Outcome: The court found that the Exclusion Clause was incorporated into the subcontract between the plaintiff and the 1st defendant.
- Category: Substantive
8. Remedies Sought
- Interim Injunction
- Restraining Order
9. Cause of Actions
- Breach of Contract
- Injunction
10. Practice Areas
- Commercial Litigation
- Construction Disputes
- Arbitration
11. Industries
- Construction
- Banking
12. Cited Cases
Case Name | Court | Affirmed | Citation | Jurisdiction | Significance |
---|---|---|---|---|---|
CKR Contract Services Pte Ltd v Asplenium Land Pte Ltd and another and another appeal and another matter | Court of Appeal | Yes | [2015] 3 SLR 1041 | Singapore | Upheld that parties are entitled to contract out of the ground of unconscionability. |
BS Mount Sophia Pte Ltd v Join-Aim Pte Ltd | High Court | Yes | [2012] 3 SLR 352 | Singapore | Discusses the circumstances where a call on a guarantee is made despite a complete absence of allegations of delay. |
Bocotra Construction Pte Ltd and others v Attorney-General | Court of Appeal | Yes | [1995] 2 SLR(R) 262 | Singapore | Excluded the use of the test espoused in American Cyanamid Co Ltd v Ethicon Ltd in determining whether a call was unconscionable or fraudulent. |
American Cyanamid Co Ltd v Ethicon Ltd | House of Lords | Yes | [1975] AC 396 | England and Wales | Test espoused in American Cyanamid Co Ltd v Ethicon Ltd excluded in determining whether a call was unconscionable or fraudulent. |
JBE Properties Pte Ltd v Gammon Pte Ltd | Court of Appeal | Yes | [2011] 2 SLR 47 | Singapore | Recognized both fraud and unconscionability as separate bases for restraining a call on a performance bond. |
GKN Contractors v Lloyds Bank plc | Not Available | Yes | GKN Contractors v Lloyds Bank plc (1985) 30 BLR 48 | England and Wales | Fraud can be established by conduct that shows that the call was invalid, and the party knowing the call to be such represented the call to the paying bank as being valid. |
Raymond Construction Pte Ltd v Low Yang Tong and another | High Court | Yes | [1996] SGHC 136 | Singapore | Unconscionability takes into account unfair or reprehensible conduct, or that which lacks good faith. |
Arab Banking Corp (B.S.C.) v Boustead Singapore Ltd | Court of Appeal | Yes | [2016] 3 SLR 557 | Singapore | The presentation of obviously non-conforming documents to support a claim, without any explanation being proffered, may be sufficient to give rise to a finding of fraud. |
Tay Long Kee Impex Pte Ltd v Tan Beng Huwah (trading as Sin Kwang Wah) | High Court | Yes | [2000] 1 SLR(R) 786 | Singapore | Innocent omissions are generally not fatal to the grant of an injunction. |
Bintai Kindenko Pte Ltd v Samsung C&T Corp | Court of Appeal | Yes | [2018] SGCA 39 | Singapore | Appeal dismissed. |
13. Applicable Rules
Rule Name |
---|
No applicable rules |
14. Applicable Statutes
Statute Name | Jurisdiction |
---|---|
Supreme Court of Judicature Act (Cap 322, 2007 Rev Ed) | Singapore |
15. Key Terms and Keywords
15.1 Key Terms
- Banker's Guarantee
- Interim Injunction
- Exclusion Clause
- Unconscionability
- Fraud
- Liquidated Damages
- Subcontract
- Adjudication Determination
15.2 Keywords
- injunction
- banker's guarantee
- construction
- contract
- fraud
- unconscionability
17. Areas of Law
Area Name | Relevance Score |
---|---|
Injunctions | 95 |
Contract Law | 70 |
Banker's Guarantee | 60 |
Construction Contracts | 50 |
Arbitration | 30 |
Evidence | 25 |
16. Subjects
- Contract Law
- Construction Law
- Banking Law
- Civil Procedure
- Injunctions