Range Construction v Goldbell Engineering: SOPA & Set-Off for Liquidated Damages
In Range Construction Pte Ltd v Goldbell Engineering Pte Ltd, the Singapore Court of Appeal addressed whether the Building and Construction Industry Security of Payment Act (SOPA) permits an employer, Goldbell Engineering Pte Ltd, to set off liquidated damages against a contractor's, Range Construction Pte Ltd, payment claim. The court dismissed Range's appeal, holding that the adjudicator had jurisdiction to consider Goldbell's set-off for liquidated damages under the pre-amendment SOPA. The court also found that the adjudicator did not breach the fair hearing rule or exceed his jurisdiction in determining the extent of Goldbell's entitlement to liquidated damages.
1. Case Overview
1.1 Court
Court of Appeal of the Republic of Singapore1.2 Outcome
Appeal Dismissed
1.3 Case Type
Civil
1.4 Judgment Type
Judgment
1.5 Jurisdiction
Singapore
1.6 Description
Singapore Court of Appeal case concerning whether SOPA permits employers to set-off liquidated damages against contractor's payment claims. Appeal dismissed.
1.7 Decision Date
2. Parties and Outcomes
Party Name | Role | Type | Outcome | Outcome Type | Counsels |
---|---|---|---|---|---|
Goldbell Engineering Pte Ltd | Respondent | Corporation | Appeal Dismissed | Won | |
Range Construction Pte Ltd | Appellant, Applicant | Corporation | Appeal Dismissed | Lost |
3. Judges
Judge Name | Title | Delivered Judgment |
---|---|---|
Tay Yong Kwang | Justice of the Court of Appeal | No |
Steven Chong | Justice of the Court of Appeal | Yes |
Quentin Loh | Judge of the Appellate Division | No |
4. Counsels
4. Facts
- Range was appointed as Goldbell's contractor for the design and erection of a six-storey workshop.
- The contract incorporated the Real Estate Developers’ Association of Singapore Design and Build Conditions of Main Contract.
- The contractual completion date was extended to 7 September 2018.
- A Temporary Occupation Permit was granted on 2 October 2018.
- Range served a payment claim on Goldbell on 2 December 2019.
- Goldbell submitted its payment response on 20 December 2019, including a set-off for liquidated damages.
- The adjudicator awarded Range $205,647.43 after deducting $852,000 in liquidated damages payable to Goldbell.
- Goldbell had not issued the Handing Over Certificate at the time of the adjudication proceedings.
- The adjudicator relied on an email dated 17 November 2018 to determine the period for liquidated damages.
5. Formal Citations
- Range Construction Pte Ltd v Goldbell Engineering Pte Ltd, Civil Appeal No 91 of 2020, [2021] SGCA 34
6. Timeline
Date | Event |
---|---|
Letter of award issued to Range Construction Pte Ltd for the Project. | |
Original contractual completion date. | |
Extended contractual completion date. | |
Temporary Occupation Permit granted. | |
Email from Range Construction's managing director regarding ongoing works. | |
Range Construction served payment claim PC 28 on Goldbell Engineering. | |
Amendments to the SOPA came into effect. | |
Goldbell Engineering submitted payment response PR 1. | |
Goldbell Engineering submitted adjudication response and written submissions. | |
Range Construction submitted reply submissions. | |
High Court judge dismissed Range Construction’s application in Range Construction Pte Ltd v Goldbell Engineering Pte Ltd [2020] SGHC 191. | |
Judgment reserved. | |
Judgment delivered. |
7. Legal Issues
- Jurisdiction of Adjudicator under SOPA
- Outcome: The court held that the adjudicator had jurisdiction to consider Goldbell's set-off for liquidated damages under the pre-amendment SOPA.
- Category: Jurisdictional
- Sub-Issues:
- Scope of adjudicator's power to consider set-offs
- Interpretation of pre-amendment SOPA
- Effect of SOPA amendments on adjudicator's jurisdiction
- Related Cases:
- [2020] SGHC 191
- [2005] NSWCA 228
- [2020] SGCA 121
- [2007] NSWSC 941
- Breach of Natural Justice
- Outcome: The court held that the adjudicator did not breach the rules of natural justice by failing to consider the significance of the grant of the TOP.
- Category: Procedural
- Sub-Issues:
- Failure to consider relevant submissions
- Fair hearing rule
- Consideration of TOP issuance
- Related Cases:
- [2018] 2 SLR 532
- [2010] 1 SLR 733
- Fair Hearing Rule
- Outcome: The court held that the adjudicator did not breach the fair hearing rule in finding that Range was liable for liquidated damages up till 17 November 2018.
- Category: Procedural
- Sub-Issues:
- Adjudicator's duty to invite submissions
- Reliance on specific evidence
- Determination of completion date
- Related Cases:
- [2018] 2 SLR 1311
8. Remedies Sought
- Setting aside part of the adjudication determination
9. Cause of Actions
- Breach of Contract
10. Practice Areas
- Construction Law
- Commercial Litigation
- Arbitration
11. Industries
- Construction
12. Cited Cases
Case Name | Court | Affirmed | Citation | Jurisdiction | Significance |
---|---|---|---|---|---|
Range Construction Pte Ltd v Goldbell Engineering Pte Ltd | High Court | Yes | [2020] SGHC 191 | Singapore | Affirmed the High Court's decision that the adjudicator had not acted in excess of jurisdiction by considering Goldbell's claim for liquidated damages. |
Coordinated Construction Co Pty Ltd v J M Hargreaves (NSW) Pty Ltd and others | New South Wales Court of Appeal | Yes | [2005] NSWCA 228 | New South Wales | Cited for the principle that progress payments for construction work should not be given a narrow construction. |
Tan Eng Hong v Attorney-General | Court of Appeal | Yes | [2012] 4 SLR 476 | Singapore | Cited for the principle that ministerial statements do not have the force of law. |
Tan Cheng Bock v Attorney-General | Court of Appeal | Yes | [2017] 5 SLR 424 | Singapore | Cited for the principle that speeches in Parliament should not be construed as statutory provisions. |
Attorney-General v Ting Choon Meng and another appeal | Court of Appeal | Yes | [2017] 1 SLR 373 | Singapore | Cited for the principle that it is for the court to determine the legal effect of a statutory provision. |
Tan Cheng Bock v Attorney-General | Court of Appeal | Yes | [2017] 2 SLR 850 | Singapore | Cited for the principle that primacy should be accorded to the text of a statutory provision over extraneous material. |
Public Prosecutor v Low Kok Heng | High Court | Yes | [2007] 4 SLR(R) 183 | Singapore | Cited for the principle that the words of a Minister must not be substituted for the text of the law. |
Orion-One Residential Pte Ltd v Dong Cheng Construction Pte Ltd and another appeal | Court of Appeal | Yes | [2020] SGCA 121 | Singapore | Distinguished; the case did not address the issue of set-offs for liquidated damages in payment responses. |
Trysams Pty Ltd v Club Constructions (NSW) Pty Ltd | Supreme Court of New South Wales | Yes | [2007] NSWSC 941 | New South Wales | Cited as an Australian case that indirectly affirms that an adjudicator has jurisdiction to take set-offs for liquidated damages into account. |
Glaziers Engineering Pte Ltd v WCS Engineering Construction Pte Ltd | Court of Appeal | Yes | [2018] 2 SLR 1311 | Singapore | Cited for the principle that it is not the duty of an adjudicator to invite submissions on each and every issue that might arise in adjudication proceedings. |
Facade Solution Pte Ltd v Mero Asia Pacific Pte Ltd | Court of Appeal | Yes | [2020] 2 SLR 1125 | Singapore | Cited for the principle that an adjudication determination is of temporal finality. |
Bintai Kindenko Pte Ltd v Samsung C&T Corp | Court of Appeal | Yes | [2018] 2 SLR 532 | Singapore | Cited for the principles regarding breach of natural justice in adjudication. |
SEF Construction Pte Ltd v Skoy Connected Pte Ltd | High Court | Yes | [2010] 1 SLR 733 | Singapore | Cited for the principles regarding breach of natural justice in adjudication. |
13. Applicable Rules
Rule Name |
---|
No applicable rules |
14. Applicable Statutes
Statute Name | Jurisdiction |
---|---|
Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed) | Singapore |
Order 95, Rule 3 of the Rules of Court (Cap 322, Rule 5, 2014 Rev Ed) | Singapore |
Section 27(5) of the Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed) | Singapore |
15. Key Terms and Keywords
15.1 Key Terms
- Building and Construction Industry Security of Payment Act
- Security of Payment Act
- SOPA
- Adjudication
- Payment Claim
- Payment Response
- Liquidated Damages
- Set-off
- Construction Contract
- Adjudication Determination
- Handing Over Certificate
- Temporary Occupation Permit
15.2 Keywords
- Construction
- SOPA
- Adjudication
- Liquidated Damages
- Set-off
- Singapore
17. Areas of Law
16. Subjects
- Construction Dispute
- Arbitration
- Contract Law
- Building and Construction Law