Ser Kim Koi v GTMS Construction: Construction Dispute - EOT, CC, Defect Rectification

In Ser Kim Koi v GTMS Construction Pte Ltd, the Appellate Division of the High Court of Singapore heard appeals regarding a construction dispute. Mr. Ser Kim Koi, the owner, appealed against GTMS Construction Pte Ltd, the contractor, and Mr. Chan Sau Yan, the architect. The dispute concerned claims for unpaid sums, counterclaims for defective works, and allegations of conspiracy. The court allowed the appeal in part, finding errors in the determination of delay length, certification process, and assessment of liquidated damages. The court affirmed the Judge’s costs orders below.

1. Case Overview

1.1 Court

Appellate Division of the High Court

1.2 Outcome

Appeal Allowed in Part

1.3 Case Type

Civil

1.4 Judgment Type

Written Judgment

1.5 Jurisdiction

Singapore

1.6 Description

Singapore case on construction dispute involving EOT, CC, and defect rectification. Appeal allowed in part, addressing errors in determining delay.

1.7 Decision Date

2. Parties and Outcomes

Party NameRoleTypeOutcomeOutcome TypeCounsels
Ser Kim KoiAppellant, Plaintiff in counterclaimIndividualAppeal Allowed in PartPartial
GTMS Construction Pte LtdRespondent, Plaintiff, Defendant in counterclaimCorporationJudgment for Plaintiff upheld with modificationsPartial
Chan Sau Yan (formerly known as trading as Chan Sau Yan Associates)Respondent, Third PartiesIndividualJudgment against Third PartyLost
CSYA Pte LtdRespondent, Third PartiesCorporationJudgment for Third PartyWon

3. Judges

Judge NameTitleDelivered Judgment
Woo Bih LiJudge of the Appellate DivisionNo
Quentin LohJudge of the Appellate DivisionYes
Chua Lee MingJudge of the High CourtNo

4. Counsels

4. Facts

  1. Mr. Ser engaged Mr. Chan as his architect under a memorandum of agreement dated 16 June 2009.
  2. GTMS was engaged to construct three bungalows on Mr. Ser's land under the Singapore Institute of Architects Articles and Conditions of Building Contract.
  3. The original completion date for the Works was 21 February 2013.
  4. GTMS requested and was granted two extensions of time (EOT 2 and EOT 3) totaling 55 days.
  5. The project failed the First TOP Inspection on 30 April 2013.
  6. Mr. Chan issued the Completion Certificate on 15 May 2013, certifying completion of the Project as of 17 April 2013.
  7. The project failed the Second TOP Inspection on 18 June 2013.
  8. The TOP was approved on 16 September 2013 by way of photographic submissions.

5. Formal Citations

  1. Ser Kim Koi v GTMS Construction Pte Ltd and others and another appeal, Civil Appeals Nos 20 and 36 of 2021, [2022] SGHC(A) 34

6. Timeline

DateEvent
Mr Ser engaged Mr Chan as his architect
Letter of Acceptance issued
SPPG informs Mr Ser of OG Box requirement
GTMS requests EOT 2
EOT 2 granted
GTMS requests EOT 3
EOT 3 granted
Final site inspection conducted
Maintenance period commences
First TOP Inspection fails
Completion Certificate issued
Second TOP Inspection fails
IC 25 issued
TOP approved
IC 26 issued
Certificate of Statutory Completion issued
Maintenance Certificate issued
Project handed over to Mr Ser
Final Certificate issued
BAPL releases the Report on the Schedule of Building Defects

7. Legal Issues

  1. Breach of Contract
    • Outcome: The court found that there was a breach of contract due to the failure to comply with specifications and the improper issuance of certificates.
    • Category: Substantive
    • Sub-Issues:
      • Improper certification
      • Defective works
      • Delay in completion
  2. Negligence
    • Outcome: The court found the architect negligent in certain aspects of his duties, leading to an award of nominal damages.
    • Category: Substantive
    • Sub-Issues:
      • Failure to exercise due care
      • Improper supervision
      • Failure to comply with statutory requirements
  3. Extension of Time
    • Outcome: The court found that the EOTs were validly granted.
    • Category: Substantive
    • Sub-Issues:
      • Force majeure
      • Due diligence
      • Delaying factor
  4. Liquidated Damages
    • Outcome: The court found that GTMS was liable for liquidated damages for a certain period, but the liquidated damages clause was inoperable due to the prevention principle.
    • Category: Substantive
    • Sub-Issues:
      • Prevention principle
      • Delay Certificate
      • Termination of Delay Certificate

8. Remedies Sought

  1. Monetary Damages
  2. Costs of Rectification
  3. Account of Profits
  4. Liquidated Damages

9. Cause of Actions

  • Breach of Contract
  • Negligence
  • Unlawful Means Conspiracy

10. Practice Areas

  • Commercial Litigation
  • Construction Law
  • Architectural Services

11. Industries

  • Construction

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
GTMS Construction Pte Ltd v Ser Kim Koi (Chan Sau Yan and Chan Sau Yan Associates, third parties)High CourtYes[2015] 1 SLR 671SingaporeCited for the application for summary judgment against Mr Ser on the basis of two Interim Payment Certificates 25 and 26.
Ser Kim Koi v GTMS Construction Pte LtdCourt of AppealYes[2016] 3 SLR 51SingaporeCited for setting aside the summary judgment and finding that neither IC 25 nor IC 26 had temporary finality.
GTMS Construction Pte Ltd v Ser Kim Koi (Chan Sau Yan (formerly trading as Chan Sau Yan Associates) and another, third parties)High CourtYes[2021] SGHC 9SingaporeCited as the judgment under appeal, where the High Court allowed GTMS’s and Mr Chan’s claims and dismissed the bulk of Mr Ser’s claims.
GTMS Construction Pte Ltd v Ser Kim Koi (Chan Sau Yan (formerly trading as Chan Sau Yan Associates) and another, third parties)High CourtYes[2021] SGHC 33SingaporeCited as the supplemental judgment on costs, in which the Judge ordered Mr Ser to pay part of the costs of the action to GTMS and Mr Chan on an indemnity basis.
Ser Kim Koi v GTMS Construction Pte Ltd and othersCourt of AppealYes[2021] 1 SLR 1319SingaporeCited for granting Mr Ser leave to appeal against the Costs Judgment.
British Electrical and Associated Industries (Cardiff) Ltd v Patley Pressings LtdEnglish High CourtYes[1953] 1 WLR 280England and WalesCited for the proposition that a force majeure clause which does not elaborate the types of events that may form the basis of force majeure is vague and uncertain.
Matsoukis v Priestman & CoKing's Bench DivisionYes[1915] 1 KB 681England and WalesCited as an example of force majeure being interpreted to cover dislocation of business owing to a universal coal strike or accidents to machinery but not bad weather, football matches or a funeral.
RDC Concrete Pte Ltd v Sato Kogyo (S) Pte Ltd and another appealCourt of AppealYes[2007] 4 SLR(R) 413SingaporeCited for the principle that the precise construction of a force majeure clause is paramount.
Holcim (Singapore) Pte Ltd v Precise Development Pte LtdCourt of AppealYes[2011] 2 SLR 106SingaporeCited for the principle that whether the affected party must have taken all reasonable steps before he can rely on the force majeure clause depends on the precise language of the clause concerned.
Tandrin Aviation Holdings Ltd v Aero Toy Store and anotherEnglish High CourtYes[2010] EWHC 40England and WalesCited for the principle that the burden of proof falls on the party seeking to rely on a force majeure clause.
Roberts v The Bury Improvement CommissionersCourt of Common PleasYes(1870) LR 5 CP 310England and WalesCited for the prevention principle, where an act of the employer prevents the contractor from completing his works on time.
Evergreat Construction Co Pte Ltd v Presscrete Engineering Pte LtdHigh CourtYes[2006] 1 SLR(R) 634SingaporeCited for the application of the prevention principle in Singapore.
Amec Civil Engineering Ltd v Secretary of State for TransportEngland and Wales Court of Appeal (Civil Division)Yes[2005] 1 WLR 2339England and WalesCited for the principle that fairness requires the contract administrator to give a speedy decision on matters where timelines pose an issue.
Magenta Resources (S) Pte Ltd v China Resources (S) Pte LtdHigh CourtYes[1996] 2 SLR(R) 316SingaporeCited for the principle that there can be no general rule as to what constitutes a situation of force majeure.
City Inn Ltd v Shepherd Construction LtdCourt of SessionYes[2007] BLR 473ScotlandMentioned as a case not dealt with by Singapore courts.
North Midland Building Limited v Cyden Homes LtdEngland and Wales Court of Appeal (Civil Division)Yes[2018] EWCA Civ 1744England and WalesMentioned as a case not dealt with by Singapore courts.
East Ham Corporation v Bernard Sunley & Sons LtdHouse of LordsYes[1966] AC 406United KingdomCited for the principle that architects are entitled to delegate their duties to other qualified professionals in the same organisation.
Phosagro Asia Pte Ltd v Piattchanine, IouriHigh CourtYes[2016] 5 SLR 1052SingaporeCited for the principle that an employer may rely on a contractual right of termination based on newfound evidence, even if not initially relied upon.
Goldlion Properties Ltd v Regent National Enterprises LtdHong Kong Court of Final AppealYes[2009] HKFCA 58Hong KongCited for the principle that whether the affected party must have taken all reasonable steps before he can rely on the force majeure clause depends on the precise language of the clause concerned.
Mears Ltd v Costplan Services (South East) Ltd and othersEngland and Wales Court of Appeal (Civil Division)Yes[2019] EWCA Civ 502England and WalesCited for the principles of practical completion.
Liang Huat Aluminium Industries Pte Ltd v Hi Tek Construction Pte LtdHigh CourtYes[2001] SGHC 334SingaporeCited for the reasons for issuing a completion certificate.
Lee Kay Guan and another v Phoenix Heights Estate (Pte) LtdHigh CourtYes[1977–1978] SLR(R) 284SingaporeCited for the distinction between readiness for occupation and the legal ability or authority to occupy.
Schindler’s Lifts (Singapore) Pte Ltd v Paya Ubi Industrial Park Pte Ltd and AnotherHigh CourtYes[2004] SGHC 34SingaporeCited for the proposition that the issuance of a CC before the TOP is not uncommon in industry practice.
Adyard Abu Dhabi v SD Marine ServicesEnglish High CourtYes[2011] EWHC 848 (Comm)England and WalesCited for the definition of concurrent delay.
Henry Boot Construction (UK) Ltd v Malmaison Hotel (Manchester) LtdTechnology and Construction CourtYes[1999] 70 Con LR 32England and WalesCited for the principle that a contractor is entitled to an extension of time where delay is caused by matters falling within the EOT clause notwithstanding the matter relied upon by the contractor is not the dominant cause of delay.
Walter Lilly & Co Ltd v Giles Patrick Cyril Mackay and anotherTechnology and Construction CourtYes[2012] EWHC 1773 (TCC)England and WalesCited for the principle that a contractor is entitled to an extension of time where delay is caused by matters falling within the EOT clause notwithstanding the matter relied upon by the contractor is not the dominant cause of delay.
Balfour Beatty Building Ltd v Chestermount Properties LtdCourt of AppealYes[1993] 32 Con LR 139England and WalesCited for the principle that the extension to the contractor would only be for the ‘net’ delay caused by the variation which would not include the ‘gross’ period up to the variation.
V Nithia (co-administratrix of the estate of Ponnusamy Sivapakiam, deceased) v Buthmanaban s/o Vaithilingam and anotherCourt of AppealYes[2015] 5 SLR 1422SingaporeCited for the principle that a claim, or a defence, which is unpleaded cannot be relied upon.
OMG Holdings Pte Ltd v Pos Ad Sdn BhdHigh CourtYes[2012] 4 SLR 231SingaporeCited for the principle that a court may permit an unpleaded point to be raised if no injustice or irreparable prejudice will be occasioned to the other party.
Ma Hongjin v SCP Holdings Pte LtdCourt of AppealYes[2021] 1 SLR 304SingaporeCited for the rationale of disallowing a claim, or a defence, that is not pleaded, is to prevent injustice from being occasioned to the party who did not have a chance to respond to the unpleaded claim or defence.
Yamashita Tetsuo v See Hup Seng LtdCourt of AppealYes[2009] 2 SLR(R) 265SingaporeCited for the principle that Contract Documents should be read and construed as a whole.
Poh Lian Development Pte Ltd v Hok Mee Property Pte Ltd and OthersHigh CourtYes[2009] SGHC 153SingaporeCited for the definition of PC Rate items.
W Hing Construction Co Ltd v Boost Investments LtdHong Kong Court of First InstanceYes[2009] HKCU 221Hong KongCited for the principle that the Court could not supply a Delay Certificate under the Hong Kong Building Contract containing the General Conditions of Contract as this was a personal function of the architect and he could not be displaced from the performance of that function.
Tropicon Contractors Pte Ltd v Lojan Properties Pte LtdHigh CourtYes[1989] 1 SLR(R) 591SingaporeCited for the principle that a Delay Certificate is a prerequisite to the employer’s right to liquidated damages.
New Civilbuild Pte Ltd v Guobena Sdn Bhd and anotherHigh CourtYes[2000] 1 SLR(R) 368SingaporeCited for the principle that a Delay Certificate is a prerequisite to the employer’s right to liquidated damages.
Samsung Corp v Chinese Chamber Realty Pte Ltd and othersHigh CourtYes[2004] 1 SLR(R) 382SingaporeCited for the principle that an arbitrator can correct or revise a Delay Certificate.
Liew Ter Kwang v Hurry General Contractor Pte LtdHigh CourtYes[2004] 3 SLR(R) 59SingaporeCited for the principle that an arbitrator can correct or revise a Delay Certificate.
Prestige v BrettellEngland and Wales Court of Appeal (Civil Division)Yes(1938) 4 All ER 346England and WalesCited for the principle that the existence of an arbitration clause will normally mean that the absence of a certificate can be remedied.

13. Applicable Rules

Rule Name
Rules of Court

14. Applicable Statutes

Statute NameJurisdiction
Public Utilities Act 1995Singapore
Public Utilities Act 2001Singapore
Energy Market Authority of Singapore Act 2001Singapore
Electricity Act 2001Singapore
Building Control ActSingapore

15. Key Terms and Keywords

15.1 Key Terms

  • Extension of Time
  • Completion Certificate
  • Temporary Occupation Permit
  • Liquidated Damages
  • Force Majeure
  • Statutory Undertaker
  • Preliminaries
  • Intumescent Paint
  • Approved Soil Mix
  • Delay Certificate
  • Termination of Delay Certificate

15.2 Keywords

  • construction
  • delay
  • defects
  • architect
  • negligence
  • EOT
  • CC
  • TOP
  • liquidated damages
  • force majeure

17. Areas of Law

16. Subjects

  • Building and Construction Dispute
  • Contract Law
  • Negligence
  • Architectural Services