Chian Teck Realty v SDK Consortium: Performance Bond Dispute in Construction Contract

In Chian Teck Realty Pte Ltd v SDK Consortium and Lonpac Insurance Bhd, the High Court of Singapore addressed a dispute over a performance bond in a construction project. Chian Teck Realty, the applicant, sought to restrain SDK Consortium, the first respondent, from claiming on a performance bond issued by Lonpac Insurance Bhd, the second respondent. The court, presided over by Lee Seiu Kin J, found that SDK's demand on the bond was invalid because it was based on a clause that had not been properly triggered. The court ordered Lonpac to be restrained from making payment to SDK pursuant to the claim on the bond made on 29 July 2022.

1. Case Overview

1.1 Court

General Division of the High Court of the Republic of Singapore

1.2 Outcome

Order for second respondent to be restrained from making payment to first respondent pursuant to the claim on the bond made on 29 July 2022. First respondent is also restrained from claiming or directing second respondent to make said payment.

1.3 Case Type

Civil

1.4 Judgment Type

Judgment

1.5 Jurisdiction

Singapore

1.6 Description

Singapore court case regarding a performance bond in a construction project. The court considered the validity of the bond call and potential fraud.

1.7 Decision Date

2. Parties and Outcomes

3. Judges

Judge NameTitleDelivered Judgment
Lee Seiu KinJudgeYes

4. Counsels

4. Facts

  1. Chian Teck was a subcontractor of SDK for a construction project at Woodlands Health Campus.
  2. Chian Teck was obliged to procure a performance bond in favour of SDK of an amount equal to 5% of the total value of the Subcontract.
  3. Lonpac issued a performance bond in favour of SDK for the sum of S$1,123,152.55.
  4. The relationship between Chian Teck and SDK deteriorated, leading to disputes and adjudication proceedings.
  5. Chian Teck served notice on SDK to terminate the contract.
  6. Lonpac sent a letter to SDK stating that it was giving SDK 90 days written notice from the expiry of the Bond of Lonpac’s intention not to extend the Bond.
  7. SDK issued a demand for payment of the entire amount secured under the Bond.

5. Formal Citations

  1. Chian Teck Realty Pte Ltd v SDK Consortium and another, Originating Application No 518 of 2022, [2023] SGHC 210

6. Timeline

DateEvent
Subcontract awarded to Chian Teck by SDK
Lonpac issued Performance Bond No Z/18/BP00/047925 in favour of SDK
Relationship between Chian Teck and SDK deteriorated
Chian Teck served notice on SDK to terminate the contract
Lonpac sent a letter to SDK stating that it was giving SDK 90 days written notice from the expiry of the Bond of Lonpac’s intention not to extend the Bond
Lonpac sent a second letter informing SDK of the same
SDK issued a demand for payment of the entire amount secured under the Bond
Hearing date
Hearing date
Hearing date
Judgment reserved

7. Legal Issues

  1. Validity of call on performance bond
    • Outcome: The court found that the call on the bond was invalid because it was based on a clause that had not been properly triggered.
    • Category: Substantive
    • Sub-Issues:
      • Compliance with condition precedents
      • Interpretation of bond clauses
    • Related Cases:
      • [2019] 4 SLR 1324
  2. Fraud in calling on performance bond
    • Outcome: The court found that Chian Teck had not met the high standard of proof necessary for showing fraud.
    • Category: Substantive
    • Sub-Issues:
      • Dishonest belief
      • Reckless indifference
    • Related Cases:
      • [2016] 3 SLR 557
      • [2019] 2 SLR 295
  3. Implied term in contract
    • Outcome: The court found that there was no room to imply the Implied Term into the Subcontract.
    • Category: Substantive
    • Sub-Issues:
      • Business efficacy
      • Officious bystander test
    • Related Cases:
      • [2013] 4 SLR 193

8. Remedies Sought

  1. Restraint of payment under the Bond
  2. Costs

9. Cause of Actions

  • Breach of Contract
  • Injunction

10. Practice Areas

  • Construction Law
  • Commercial Litigation

11. Industries

  • Construction
  • Insurance

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
Shanghai Electric Group Co Ltd v PT Merak Energi Indonesia and anotherHigh CourtYes[2010] 2 SLR 329SingaporeCited to support the principle that a performance bond is 'as good as cash' because it provides certainty of payment from a reputable financial institution.
Master Marine AS v Labroy Offshore Ltd and othersCourt of AppealYes[2012] 3 SLR 125SingaporeCited for the principle that the performance bond is a contract between the beneficiary and the financial institution, and as between them, the underlying contract is not relevant.
Arab Banking Corp (B.S.C.) v Boustead Singapore LtdCourt of AppealYes[2016] 3 SLR 557SingaporeCited for the principle that the court will only grant an injunction where the demand is made fraudulently, on the ground that 'fraud unravels all'.
Bocotra Construction Pte Ltd and others v Attorney-GeneralCourt of AppealNo[1995] 2 SLR(R) 262SingaporeCited for setting a high standard of proof for fraud in demanding payment under a performance bond.
Sunrise Industries (India) Ltd v PT OKI Pulp & Paper Mills and anotherHigh CourtYes[2018] SGHC 145SingaporeCited for setting a high standard of proof for fraud in demanding payment under a performance bond.
Dauphin Offshore Engineering & Trading Pte Ltd v The Private Office of His Royal Highness Sheikh Sultan bin Khalifa bin Zayed bin Zayed Al NahyanHigh CourtNo[1999] SGHC 201SingaporeCited for tracing the development of unconscionability as a ground for restraining demands on performance bonds.
GHL Pte Ltd v Unitrack Building Construction Pte Ltd and anotherCourt of AppealYes[1999] 3 SLR(R) 44SingaporeCited for confirming unconscionability as a ground to restrain demands on performance bonds.
CKR Contract Services Pte Ltd v Asplenium Land Pte Ltd and another and another appeal and another matterCourt of AppealNo[2015] 3 SLR 1041SingaporeCited as an example of parties agreeing that the performance bond cannot be restrained on the ground of unconscionability.
Sembcorp Marine Ltd v PPL Holdings Pte Ltd and another and another appealCourt of AppealYes[2013] 4 SLR 193SingaporeCited for the three-step requirement for the implication of contract terms.
Cargill International SA v Bangladesh Sugar and Food Industries CorpEnglish CourtNo[1996] 4 All ER 563England and WalesCited for the proposition that terms can be implied into the underlying contract between contractor and sub-contractor which would circumscribe the buyer’s rights under his collateral guarantee with the guarantor, notwithstanding that the guarantee and underlying contract are independent at law.
Ryobi Tactics Pte Ltd v UES Holdings Pte Ltd and another and another matterCourt of AppealYes[2019] 4 SLR 1324SingaporeCited for the principle that a call on the performance bond which stipulates such requirements would be restrained in the absence of strict compliance.
Bintai Kindenko Pte Ltd v Samsung C&T Corp and anotherCourt of AppealYes[2019] 2 SLR 295SingaporeCited for the requirements to establish a strong prima facie case that the beneficiary called on the bond with the knowledge that its demand was invalid, without belief in the validity of its demand, or with indifference to whether the demand was valid or not.
1L30G Pte Ltd v EQ Insurance Co LtdHigh CourtYes[2017] 5 SLR 1106SingaporeCited for the principle that the postal acceptance rule did not apply to the clause, and that the clause was only satisfied when the plaintiff in that case had actually received the notice of non-renewal.
Golden Harvest Films Distribution (Pte) Ltd v Golden Village Multiplex Pte LtdCourt of AppealYes[2007] 1 SLR(R) 940SingaporeCited for the principle that where an express term of the contract governs the legal relationship between the parties, there is no scope for the implication of a term.

13. Applicable Rules

Rule Name
Rules of Court 2021 Order 13 Rule 1

14. Applicable Statutes

Statute NameJurisdiction
Supreme Court of Judicature Act (Cap 322) Section 18(2)Singapore
Supreme Court of Judicature Act (Cap 322) First ScheduleSingapore
Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed)Singapore

15. Key Terms and Keywords

15.1 Key Terms

  • Performance bond
  • Subcontract
  • Unconditional demand
  • Fraud
  • Implied term
  • Notice of non-extension
  • Condition precedent
  • Building and Construction Industry Security of Payment Act

15.2 Keywords

  • performance bond
  • construction contract
  • injunction
  • fraud
  • Singapore
  • building and construction law

17. Areas of Law

16. Subjects

  • Building and Construction Law
  • Contract Law
  • Performance Bonds